Guidance A: The information management function and resources
Nội dung
- 2 | Guidance Part A Edition 2 - February 2021
- Message from the
- 19650 series, which first developed out of the
- 3 | Guidance Part A Edition 2 - February 2021
- Acknowledgments
- 4 | Guidance Part A Edition 2 - February 2021
- About BS EN ISO 19650
- Forewords in ISO 19650 Parts 1 and 2, and a
- 5 | Guidance Part A Edition 2 - February 2021
- Abbreviations and acronyms
- 6 | Guidance Part A Edition 2 - February 2021
- About this guidance document
- 7 | Guidance Part A Edition 2 - February 2021
- 8 | Guidance Part A Edition 2 - February 2021
- 9 | Guidance Part A Edition 2 - February 2021
- 1.2 The information management function
- 5.1.1 5.2.1 5.3.1 5.4.1 5.5.1 5.6.1 5.7.1 5.8.1
- 5.1.2 5.2.2 5.3.2 5.4.2 5.5.2 5.6.2 5.7.2 5.8.2
- 5.1.3 5.2.3 5.3.3 5.4.3 5.5.3 5.6.3 5.7.3
- 5.1.4 5.2.4 5.3.4 5.4.4 5.6.4 5.7.4
- 5.1.5 5.3.5 5.4.5 5.6.5
- 5.1.6 5.3.6 5.4.6
- 5.1.7 5.3.7 5.4.7
- 5.1.8 Information procurement Information planning Information production
- 1.2 The information management function
- 10 | Guidance Part A Edition 2 - February 2021
- 11 | Guidance Part A Edition 2 - February 2021
- 12 | Guidance Part A Edition 2 - February 2021
- 1 3 2 C
- 3 2 Delivery Team C
- 3 Task Team(s)
- 13 | Guidance Part A Edition 2 - February 2021
- 14 | Guidance Part A Edition 2 - February 2021
- 15 | Guidance Part A Edition 2 - February 2021
- 19650 specifically). This may help identify and
- 16 | Guidance Part A Edition 2 - February 2021
- 17 | Guidance Part A Edition 2 - February 2021
- 18 | Guidance Part A Edition 2 - February 2021
- 19 | Guidance Part A Edition 2 - February 2021
- 20 | Guidance Part A Edition 2 - February 2021
- 21 | Guidance Part A Edition 2 - February 2021
- 1 Oxford English Dictionary
- 22 | Guidance Part A Edition 2 - February 2021
- 23 | Guidance Part A Edition 2 - February 2021
- 24 | Guidance Part A Edition 2 - February 2021
- 2 Annex A. It provides an expanded list of adaptation. Examples of how this might be
- 25 | Guidance Part A Edition 2 - February 2021
- 26 | Guidance Part A Edition 2 - February 2021
- 27 | Guidance Part A Edition 2 - February 2021
- 28 | Guidance Part A Edition 2 - February 2021
- Summary of the delivery Lead Appointment For 2 5.3.4 Establish the delivery
- 29 | Guidance Part A Edition 2 - February 2021
- Summary of the prospective delivery team’s capability +
- 30 | Guidance Part A Edition 2 - February 2021
- 31 | Guidance Part A Edition 2 - February 2021
Information management according to BS EN ISO 19650 Guidance Part A The information management function and resources Edition 2 Published by
Editions Edition 1 September 2020 First release as guidance A. Note the resources text first appeared in ISO 19650 Part 2 guidance edition 3 Edition 2 February 2021 Inclusion of new section 1.8 covering the Information management assignment matrix Nothing in this guidance constitutes legal advice or gives rise to a solicitor/client relationship. Specialist legal advice should be taken in relation to specific circumstances. The contents of this guidance are for general information purposes only. Permission to reproduce extracts from the ISO 19650 series is granted by BSI Standards Limited (BSI) and the copyright in Figure 3 used in this report belongs to BSI. No other use of this material is permitted. British Standards can be obtained in PDF or hard copy formats from the BSI online shop: http://www.bsigroup.com/Shop or by contacting BSI Customer Services for hard copies only: Tel: +44 (0)20 8996 9001, Email: cservices@bsigroup.com Any data or analysis from this guidance must be reported accurately and not used in a misleading context. If using any information from this report, then its source and date of publication must be acknowledged. © COPYRIGHT 2020 the Editors, Authors and Contributors named herein
2 | Guidance Part A Edition 2 - February 2021
The information management function and resources
Message from the
UK BIM Alliance Chair Author: Dr Anne Kemp OBE Chair - UK BIM Alliance The UK BIM Framework provides the the “end in mind” and consideration from an fundamental step towards digital organizational, whole life perspective. This transformation of the UK’s built environment then informs the detailed requirements right industry. The Framework is based on the ISO down to appointment level.
19650 series, which first developed out of the
UK’s former BIM Level 2, but incorporates The work behind developing this Guidance and anticipates global and future digital has been considerable. I would like to thank perspectives. Sarah Davidson and David Churcher for their tireless commitment in continuing to bring this The UK BIM Framework embraces and assists work together – I so enjoy working with you in the implementation of the standards both. Secondly, I would like to thank the many for managing information for the whole authors who have contributed so generously life of assets of the built environment. The to the writing of the Guidance – and been so Framework anticipates the potential for patient in the criticisms and changes that have integration across portfolios. The Framework been required of them. Finally, I would like to provides extensive Guidance which continues thank the many people who have spared time to be developed, including the addition of to review and feedback on the Guidance – the supplementary tools and materials to enable Focus Groups in particular, but also those who a firm basis for the evolving National Digital have contacted us separately. Without this Twin Programme. feedback we would not be able to incorporate the wide-ranging experience and testing which This Guidance has been developed to help is occurring around the industry. industry to implement the concepts and principles of the ISO 19650 series upon which We welcome your continued feedback and the UK BIM Framework is based. It has shared experiences. You can provide this via been continually updated to keep track of guidancefeedback@ukbimframework.org. the publication of the different parts of ISO 19650, and to reflect lessons learnt as further experience is gained in its implementation. The key parts of ISO 19650 are now all in place, allowing us to realize information management throughout the whole life of built environment assets. It provides for traditional ways of working entailing exchange of information via files, but also caters for shifts towards data exchange. The key is being specific about what information is required and how it is to be delivered. This needs forethought around what should be
3 | Guidance Part A Edition 2 - February 2021
The information management function and resources
Acknowledgments
This guidance represents the collaborative efforts of the following people and organizations Editors David Churcher Hitherwood Consulting Ltd Sarah Davidson University of Nottingham Anne Kemp Atkins Authors Andy Boutle Kier Author: Section 1 Sarah Davidson University of Nottingham Author: Section 2 Rob Jackson Bond Bryan Author: Section 1 Contributor Mo Shana’a Morta Production Centre for Digital Built Britain
4 | Guidance Part A Edition 2 - February 2021
The information management function and resources
About BS EN ISO 19650
The BS EN ISO 19650 series of standards Standards within the ISO 19650 series are (herein after referred to as the ISO 19650 available at www.bsigroup.com. series) is an international standard of good Visit www.ukbimframework.org to see how the practice. It defines information management ISO 19650 standards plus other standards principles and requirements within a within the UK BIM Framework map to the broader context of digital transformation design, build, operate and integrate process. in the disciplines and sectors of the built environment (including construction and asset management industries). Its implementation in the UK is supported by UK National
Forewords in ISO 19650 Parts 1 and 2, and a
UK National Annex in ISO 19650 Part 2. The ISO 19650 series replaces some of the existing British Standards and Publicly Available Specifications relating to information management using building information modelling (BIM). It is part of a landscape, or ecosystem, of national and international standards supporting information management processes and technical solutions. It considers all information whether it is a construction programme, a record of a meeting, a geometrical model or a contract administration certificate. Building information modelling (BIM) plays a key part in the management of information because it provides a methodology that helps us to structure information so that technology can process it. Structuring information using industry standards helps to improve interoperability. This means that information can be joinedup by both people and technology, which then enables us to extract more valuable knowledge from it. Using the same information structures throughout industry generates consistency, repetition and predictability. This brings real efficiency gains for businesses and provides the data architecture for the connected future.
5 | Guidance Part A Edition 2 - February 2021
The information management function and resources
Abbreviations and acronyms
This guidance includes a number of abbreviations and acronyms as set out in Table 1. Table 1: Abbreviations and acronyms Abbreviation or acronym Term AIR Asset information requirements BEP BIM execution plan BIM Building information modelling COBie Construction-Operations Building information exchange IT Information technology MIDP Master information delivery plan PIR Project information requirements RACI Responsible, accountable, consulted, informed TIDP Task information delivery plan
6 | Guidance Part A Edition 2 - February 2021
The information management function and resources
About this guidance document
(executive summary) The guidance framework supports the UK Guidance A is written to support the implementation of the ISO 19650 series. implementation of each published ISO 19650 This guidance document (guidance A) sits standard. within an overall guidance framework as shown in Figure 1: ISO 19650 Guidance Part 1 Concepts ISO 19650 ISO 19650 ISO 19650 ISO 19650 Guidance Part 2 Guidance Part 3 Guidance Part 4 Guidance Part 5 Delivery phase Operational phase (To be confirmed) (To be confirmed) ISO 19650 ISO 19650 ISO 19650 ISO 19650 ISO 19650 ISO 19650 Guidance A Guidance B Guidance C Guidance D Guidance E Guidance F The Open data, Facilitating the Developing Tendering and Information information buildingSMART CDE (workflow information appointments delivery management and COBie and technical requirements planning function & solutions) resources Figure 1: ISO 19650 guidance framework
7 | Guidance Part A Edition 2 - February 2021
The information management function and resources Who is this guidance written for? Key takeaways This guidance is for parties, teams and • Information management is the individuals accountable and/or responsible management and execution of tasks relating to the definition of information for undertaking the information management requirements, information production, and function. delivery and checking. Who is this guidance of particular interest • The appointing party has overall accountability for assigning responsibility to and why? of information management functions to This guidance considers the information their appointed parties. management function and resources needed • Every party within the project team has for successful information management. It information management functions they is relevant to parties, teams and individuals will need to fulfill involved in implementing the ISO 19650 series • The guidance refers to resources and not across a project, within an appointment or documents because they do not need to within an organization. exist in documents and do not need to be standalone. • Adopting the same information structures throughout industry generates consistency, repetition and predictability, and enables achieving better project outcomes. • Resources and content created for successful information management should not be created in isolation of other project functions and should be authored with the right level of consideration to how the content cascades through the delivery team. As with all guidance supporting the UK BIM Framework, we invite comment and feedback on this guidance A at guidancefeedback@ukbimframework.org
8 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.0 About the information
management function Author: Andy Boutle Kier Rob Jackson Bond Bryan
1.1 Information management and why it is needed
Information management at its simplest is the These enablers demand collaborative working management and execution of tasks relating and are reliant on the effective management to the definition of information requirements of information across the whole life of assets as well as information production, checking to help improve our built environment. and delivery. Everyone making up a project team consequently has an involvement and The necessity for good information interaction with information management in management is heightened further with the varying degrees. It is not a new concept and move to digital ways of working. In order to has existed in some shape or form ever since unlock efficiencies and effective use and reuse information production was carried out by of information we need to specify, produce, hand. check, approve and exchange information in a consistent and structured manner. While the use of technology brings many benefits, It is fundamental to understand that it relies on these consistent and structured information management applies to ALL approaches. The risks generated by poor information, collectively referred to as an procurement and management of information “information model”. An information model delivered digitally could be considered is a set of structured and/or unstructured greater than its analogue predecessor via, for information containing any combination of example, inappropriate access or distribution geometrical information, alphanumerical of information and security breaches. information and documentation In recent years, the importance of good It is essential that the industry focuses on information management with documented “information as an asset” as much as the responsibility and accountability for the physical asset itself. At both a business activities and tasks involved has become vital. and project level, outcomes are determined A proper focus on information management by decisions, and decisions are based on can help to achieve better project outcomes information. We therefore need to make sure through, for example: that information management is embedded and treated with the same importance as • Improved coordination and communication design, project, and asset management. • Better quality information production • Timely information delivery • Mitigated rework, unnecessary waste and cost • Effectively informed decision making • More accurate audit trails/record keeping.
9 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.2 The information management function
The information management function For an appointing party, it is critical that encompasses the collective responsibility and the information management function authority for the information management is clearly assigned prior to engaging process set out in ISO 19650-2. any lead appointed parties such as the project manager, cost consultant or design Clause 5.1.1 specifically covers the appointing consultants. party’s (client’s) project wide assignment of the information management function, The clause activities for the information with clause 5.3.1 covering the appointment management process are summarized in level equivalent across lead appointed ISO 19650-2 Figure 3, and it is important to party (tier 1) delivery teams. Every clause understand that most of these activities are (activity) from ISO 19650-2 will therefore undertaken at an appointment level. need to be assigned across the project team Figure 2 below (which is based on ISO appropriately with individuals nominated 19650-2 Figure 3) shows the clause numbers to fulfil activities and tasks as the project (activities) making up the information progresses. management process, and which of these activities are applicable to each party when The very first step by any party should be to performing their information management understand the context, purpose and scope function. The background colour indicates of their information management function, the predominant party for the clause as a and then assign the various responsibilities whole (i.e. clause 5.3 = lead appointed party). and accountabilities for the required activities The sub-clause reference colour indicates the appropriately. party primarily responsibility for the subclause activity (i.e. 5.1.1 = appointing party). We can see that every party has at least one activity to carry out in each of the information procurement, information planning and information production stages of the process. Activities undertaken per project Activities undertaken per lead appointed party appointment Activities undertaken per appointed party appointment
5.1.1 5.2.1 5.3.1 5.4.1 5.5.1 5.6.1 5.7.1 5.8.1
5.1.2 5.2.2 5.3.2 5.4.2 5.5.2 5.6.2 5.7.2 5.8.2
5.1.3 5.2.3 5.3.3 5.4.3 5.5.3 5.6.3 5.7.3
5.1.4 5.2.4 5.3.4 5.4.4 5.6.4 5.7.4
5.1.5 5.3.5 5.4.5 5.6.5
5.1.6 5.3.6 5.4.6
5.1.7 5.3.7 5.4.7
5.1.8 Information procurement Information planning Information production
Information model progressed by delivery team(s) Appointing party clauses Lead appointed party clauses Appointed party clauses Figure 2: Information management process responsibilities and activities
10 | Guidance Part A Edition 2 - February 2021
The information management function and resources Every party within the project team has Key points to note information management functions they will need to fulfil by assigning the associated • The appointing party (client) has overall activities to appropriate individuals within accountability for assigning responsibility their organization. See section 1.4 in this of information management functions to guidance. their lead appointed parties and should be vigilant to these being carried out as Wherever possible it is recommended that required. individuals within organizations are upskilled • Lead appointed parties could be asked for self-delivery and continuous improvement. to support and input to appointing party However, a third party can be appointed resources (for the purposes of information under an agreed scope of services to carry out management) where the client needs all or some of these information management assistance but is not willing to formally activities. appoint a third party. • Individuals in existing roles that are Readers familiar with superseded PAS 1192- assigned information management 2:2013 will recall information management activities may consider these secondary responsibilities defined under specific roles in importance to their usual role when assumed by members of the project team particularly busy or under pressure. This (project information manager, task team risk needs to be recognized and managed. manager, task information manager etc.). The ISO 19650 series moves away from this approach and intends that the information management function is embedded into existing roles.
11 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.3 The information management function in the context of
multiple lead appointed parties A lead appointed party (tier 1) is any organization that has a direct appointment with the appointing party (client). Therefore, at any one stage in a project there will often be more than one lead appointed party. Even on small projects the client will appoint separate consultants and advisers during the design stage, each will therefore be a lead appointed party. Some lead appointed parties (e.g. client appointed design consultants, main contractor) will appoint other organizations or internal teams, as task teams, to form their delivery teams. Other lead appointed parties (e.g. client’s project manager, cost consultant) will be the only organizations in their delivery teams, therefore their information management functions will be proportionally simpler. Lead appointed party information management functions are at an appointment level and on behalf of their delivery team, so each lead appointed party must prepare the resources required as part of their tender response, and if successful the resources required during their appointment, as shown in Table 2. Table 2: Resources to be prepared by a lead appointed party Tender (Pre-appointment) BIM execution response plan phase (5.3) Capability and capacity summary Mobilization plan Risk register Appointment BIM execution plan phase (5.4) Detailed responsibility matrix Lead appointed party’s exchange information requirements Master information delivery plan
12 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1 3 2 C
C C Main Contractor 2 B ... Key: Architect ... B A Appointing Party A Client 3 B Lead Appointed Party C Appointed Party Client’s project B 2 manager 1 Project Team
3 2 Delivery Team C
3 Task Team(s)
Figure 3: Interfaces between parties and teams The project wide information resources In this example the client has appointed (specifically the project’s information standard an architect and has also engaged a main and the project’s information production contractor to provide engineering design and methods and procedures) along with each build services. The client has appointed a exchange information requirements (EIR) project manager to ensure the delivery teams received by each lead appointed party, and project align to the required delivery should drive consistency when preparing outcomes. As lead appointed parties, they their required resources (see Table 2). This are each required to produce the resources should enable collaborative working practices as per Table 2 for their tender response and with commonality across the lead appointed appointment phases. parties and their delivery teams. If lead appointed parties are required to work in very close collaboration (such as client appointed design consultants), it would be considered good practice for the authors of the required resources from each organization to communicate during the information planning stage (especially when developing each delivery team’s BIM execution plan). This will drive out potential inconsistencies when finalizing their own resources. This should be done via the project’s common data environment. For example, consider a scenario where there are three lead appointed parties at a particular work stage on a project, as indicated in Figure 3.
13 | Guidance Part A Edition 2 - February 2021
The information management function and resources An example of the high-level scope and Note: Even as the client’s project manager, structure for these lead appointed parties this organization is still producing along with any considerations in terms of the information deliverables in response to resources required is discussed below: information requirements. Therefore, it is correct that a BIM execution plan (essentially Architect a method statement for information delivery) is required as well as a master This organization has in-house expertise information delivery plan (essentially a for the required scope of services covering task information delivery plan (TIDP) in architecture, interior design and landscape this case as the only party in the delivery architecture. The organization is a lead team). It is acknowledged that the content appointed party with internal task teams, of these resources is likely to be less detailed forming a delivery team. All information compared with the other lead appointed resources (see Table 2) will be required for parties who have more extensive exchange the tender response and appointment stage information requirements. for this lead appointed party. Main contractor This organization is a management contractor that will appoint a supply chain to deliver the design and build scope of services required. The organization is a lead appointed party with external task teams, forming a delivery team. All information resources (see Table 2) will be required for the tender response and appointment phase for this lead appointed party. Client’s project manager This organization is delivering a project management service on behalf of the client. The project manager will typically manage the tender process, be responsible for creating and monitoring the strategic programme of works, maintaining progress trackers, producing stage reports, meeting agendas/minutes etc. In this example, this organization is a lead appointed party with no other appointed parties, and therefore is in itself the delivery team made up of internal task team(s). All information resources (see Table 2) will be required for the tender response and appointment phase, with the exception of the lead appointed party’s exchange information requirements (as there is no requirement for any appointed parties).
14 | Guidance Part A Edition 2 - February 2021
The information management function and resources Key points to note • An appointing party with multiple lead appointed parties will need to review multiple BIM execution plans and master information delivery plans (MIDPs). These may be delivered in different structures and formats. • An appointing party could produce templates as shared resources to drive consistency of structure and format. This could be disruptive for lead appointed parties who have established company-wide templates already approved in their quality management systems. • If there are any errors contained in shared resources produced by an appointing party intended for use by other parties within the project team, this would introduce an element of risk for consideration. These shared resources should be tested during mobilization where appropriate. • When there are lead appointed parties with significantly different scopes of work and information deliverables, appointing party template(s) may be inappropriate.
15 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.4 Developing ISO 19650-2 information management activities into
a detailed matrix of tasks ISO 19650-2 includes an information An example of how a lead appointed party management assignment matrix in Annex such as a main contractor might approach A, as noted in clause 5.1.1. This is a useful a more detailed information management resource for an appointing party to use to function assignment matrix is shown in Figure help form a scope of services when appointing 4. This example shows how a list of tasks a lead appointed party or third party to carry might be developed under the activity clause out all or part of the information management 5.4 from ISO 19650-2. function. It provides a summary of the clause activities involved in the information An example of how an appointed party management process in the form of a RACI such as a building services sub-contractor (responsible, accountable, consulted, informed) might approach a more detailed information matrix. management function assignment matrix is shown in Figure 5. This example shows how Some clause activities from ISO 19650-2 a list of tasks might be developed under ISO may cover one task, for example preparing 19650-2 activity clauses 5.3, 5.4, 5.6 and 5.7 exchange information requirements. Other 2. Clause 5.6.2 (generate information) is not activities may involve many tasks, for example included as assigning tasks associated with the activity of generating information this clause should be via the responsibility could include tasks such as producing matrices and the TIDPs and MIDP. models, drawings, schedules, clash detection procedures, programme simulations and COBie. Any party may choose to develop a more detailed information management function assignment matrix based on Annex A (although this is not a requirement of ISO
19650 specifically). This may help identify and
assign the specific tasks making up activities that are relevant to them. This expanded approach can be used by the organization to allocate or identify responsibility, accountability, consulted, informed (RACI) to individuals within their internal team, and to indicate RACI for other organizations engaged in the project team. Any activities associated with clause 5.6.2 ‘Generate information’ should be dealt with through the responsibility matrices and information delivery plans. Refer to ISO 19650 guidance F Information delivery planning. Next page Figure 4: Example approach for a main contractor - expanded information management function assignment matrix
16 | Guidance Part A Edition 2 - February 2021
The information management function and resources Appointing Appointed Information management assignment matrix party Lead appointed party party Main contractor example Key: R Responsible for undertaking activity/task party task and A Accountable for activity/task completion controller surveyor C Consulted during activity/task third manager manager manager I Informed following activity/task completion advisor specialist manager engineer ID Activity/task Source Client Client's Bid Design Project Site Quantity Planner SHE Quality Document BIM Consultantsubcontractorteams Information management process - ISO 19650- 4 Appointment 2; 5.4 ISO 19650-2; 4.1 Confirm the delivery team's BIM execution plan 5.4.1 Develop the delivery team's BIM execution plan ISO 19650-2; 4.1.1 C I A/R C in agreement with the supply chain, including: 5.4.1 Confirm the names of the individual(s) who will ISO 19650-2; 4.1.2 C C C I A/R C undertake the information management function 5.4.1 a) Update the delivery team's information delivery ISO 19650-2; 4.1.3 A/R C strategy (as required) 5.4.1 b) Update the delivery team's high-level ISO 19650-2; 4.1.4 A/R C responsibility matrix (as required) 5.4.1 c) Confirm and document the delivery team's ISO 19650-2; 4.1.5 proposed information production methods and A/R C 5.4.1 d) procedures Agree with the appointing party any additions ISO 19650-2; 4.1.6 or amendments to the project's information C C A/R I 5.4.1 e) standard Confirm the schedule of software, hardware and ISO 19650-2; 4.1.7 C C I I I I A/R C IT infrastructure the delivery team will use 5.4.1 f) Establish the delivery team's detailed ISO 19650- 4.2 responsibility matrix 2; 5.4.2 Refine the high-level responsibility matrix to ISO 19650-2; 4.2.1 R C I A/R establish the detailed responsibility matrix 5.4.2 Share the detailed responsibility matrix for 4.2.2 n/a R I R A/R C supply chain review and comment Establish the lead appointed party's exchange ISO 19650- 4.3 information requirements 2; 5.4.3 Establish the lead appointed party's exchange ISO 19650-2; 4.3.1 A/R I R information requirements 5.4.3 ISO 19650-2; 4.3.2 Define each information requirement A/R I R 5.4.3 a) Establish the level of information need required ISO 19650-2; 4.3.3 A/R I R to meet each information requirement 5.4.3 b) Establish the acceptance criteria for each ISO 19650-2; 4.3.4 A/R I R information requirement 5.4.3 c) Establish the dates, relative to the project's ISO 19650-2; 4.3.5 A/R I R information delivery milestones 5.4.3 d) Establish the supporting information that the appointed part might need, to fully understand ISO 19650-2; 4.3.6 R I A/R or evaluate each information requirement or its 5.4.3 e) acceptance criteria ISO 19650- 4.4 Establish the task information delivery plan(s) 2; 5.4.4 Establish a task information delivery plan
4.4.1 template (if not provided by the appointing n/a I A/R
party within any shared resources) Establish and maintain a task information ISO 19650-2; 4.4.2 C I I C A/R delivery plan throughout the appointment 5.4.4 ISO 19650- 4.5 Establish the master information delivery plan 2; 5.4.5 Aggregate task information delivery plans from ISO 19650-2; 4.5.1 each task team to establish the delivery team's R A/R I 5.4.5 master information delivery plan (MIDP) Baseline deliverables and dates within the master ISO 19650-2; 4.5.2 A/R I information delivery plan 5.4.5 Inform each task team and notify if any changes ISO 19650-2; 4.5.3 R A/R R I I are required to the task information delivery plan 5.4.5 Inform the appointing party of any risks or ISO 19650-2; 4.5.4 issues which could impact on the project delivery I C A/R C C C Figure 4: Examplemilestonesapproach for a main contractor - expanded5.4.5 information management function assignment matrix
17 | Guidance Part A Edition 2 - February 2021
The information management function and resources Appointing Appointed Information management assignment matrix party Lead appointed party party Main contractor example Key: R Responsible for undertaking activity/task party task and A Accountable for activity/task completion controller surveyor C Consulted during activity/task third manager manager manager I Informed following activity/task completion advisor specialist manager engineer ID Activity/task Source Client Client's Bid Design Project Site Quantity Planner SHE Quality Document BIM Consultantsubcontractorteams
4.6 Update shared resources n/a
Update the project’s information standard with agreed additions or amendments proposed by lead appointed parties within their pre-
4.6.1 appointment BIM execution plans and n/a A/R I I I I I
subsequently throughout their appointment (including any updates required by the security management plan) Update the project’s information production methods and procedures with agreed additions or amendments proposed by lead appointed
4.6.2 parties within their pre-appointment BIM n/a A/R I I I I I
execution plans and subsequently throughout their appointment (including any updates required by the security management plan) Complete lead appointed party's appointment ISO 19650- 4.7 documents 2; 5.4.6 Complete lead appointed party's appointment ISO 19650-2; 4.7.1 A/R I I I documents 5.4.6 Ensure the appointing party's exchange ISO 19650-2; 4.7.2 information requirements are included in the A/R I I I 5.4.6 appointment Ensure the project's information standard is ISO 19650-2; 4.7.3 included in the appointment with any agreed A/R I I I 5.4.6 additions or amendments Ensure the project's information production methods and procedures is included in the ISO 19650-2; 4.7.4 A/R I I I appointment with any agreed additions or 5.4.6 amendments Ensure the delivery team's BIM execution plan is ISO 19650-2; 4.7.5 A/R I I I included in the appointment 5.4.6 Ensure the delivery team's master information ISO 19650-2; 4.7.6 delivery plan (MIDP) is included in the A/R I I I 5.4.6 appointment Ensure the project's information protocol is 4.7.7 n/a A/R I I I included within the appointment Manage change control process associated
4.7.8 to lead appointed party(s) appointment n/a A/R I I I
documentation Complete appointed party's appointment ISO 19650- 4.8 documents 2; 5.4.7 Complete appointed party's appointment ISO 19650-2; 4.8.1 documents for agreement with each appointed R A/R C I 5.4.7 party Ensure the lead appointed party's exchange ISO 19650-2; 4.8.2 information requirements are included in the R A/R C I 5.4.7 appointment Ensure the project's information standard is ISO 19650-2; 4.8.3 included in the appointment with any agreed R A/R C I 5.4.7 additions or amendments Ensure the project's information production methods and procedures is included in the ISO 19650-2; 4.8.4 R A/R C I appointment with any agreed additions or 5.4.7 amendments Ensure the delivery team's BIM execution plan is ISO 19650-2; 4.8.5 R A/R C I included in the appointment 5.4.7 Ensure the agreed task information delivery plan ISO 19650-2; 4.8.6 R A/R C I (TIDP) is included in the appointment 5.4.7 Ensure the project's information protocol is 4.8.7 n/a R A/R C I included within the appointment Manage change control process associated to 4.8.8 n/a R A/R C I appointed party(s) appointment documentation
18 | Guidance Part A Edition 2 - February 2021
The information management function and resources Lead appointed Subcontractor appointed party Information management assignment matrix: Appointingparty Appointed party Building services sub-contractor example party Key: R Responsible for undertaking activity/task party task A Accountable for activity/task completion engineer controller engineer surveyor C Consulted during activity/task third manager manager chain I Informed following activity/task completion Contractor technician(s) specialist ID Activity/task Source Client Client's Main Design Project Mechanical Electrical Quantity Document CAD BIM Supplyteams Information management process - Collaborative ISO 19650-2; 6 production of information 5.6 Check availability of reference information and ISO 19650-2; 6.1 shared resources 5.6.1 Check that relevant reference information and ISO 19650-2; 6.1.1 shared resources is available within the project's I I R C A/R I 5.6.1 common data environment Inform the lead appointed party and assess the potential impact of not having access to ISO 19650-2; 6.1.2 I R A/R C R reference information and shared resources could 5.6.1 have on the task information delivery plan (TIDP) BS EN ISO
6.2 Generate information 19650-
2:2018; 5.6.2 Generate information in accordance with ISO 19650-2; 6.2.1 I A/R R R R R C R R R respective task information delivery plan (TIDP) 5.6.2 a) Coordinate and cross-reference all information with information shared within the project’s ISO 19650-2; 6.2.2 common data environment, in accordance with I R I R R I A/R R C R 5.6.2 c) the project’s information production methods and procedures Spatially coordinate geometrical models with other geometrical models shared with the ISO 19650-2; 6.2.3 I I I I I A/R C R appropriate suitability, residing within the 5.6.2 d) project’s common data environment ISO 19650-2; 6.3 Undertake quality assurance check 5.6.3 Undertake a quality assurance check of each information container, in accordance with the ISO 19650-2; 6.3.1 project's information production methods and I C I A/R R C R 5.6.3 procedures, prior to undertaking a review of the information within it ISO 19650-2; 6.4 Review information and approve for sharing 5.6.4 Undertake a review of the information within each information container, in accordance with ISO 19650-2; 6.4.1 the project's information production methods and I A/R I R R I I C C C 5.6.4 procedures, prior to sharing within the project's common data environment ISO 19650-2; 6.5 Information model review 5.6.5 Undertake a review of the information model, in accordance with the project's information ISO 19650-2; 6.5.1 production methods and procedures, to facilitate I R I I I I I A/R I 5.6.5 the continuous coordination of information across each element of the information model Information management process - Information ISO 19650-2; 7 model delivery 5.7 Submit information model for lead appointed ISO 19650-2; 7.1 party authorization 5.7.1 Submit information to the lead appointed party ISO 19650-2; 7.1.1 for authorization within the project's common I R R C C I A/R C R I 5.7.1 data environment ISO 19650-2; 7.2 Review and authorize the information model 5.7.2 Review the information model in accordance with ISO 19650- 7.2.1 the project's information production methods and A/R I I I 2; 5.7.2 procedures Figure 5: Example approach for a building services sub-contractor - expanded information management function assignment matrix
19 | Guidance Part A Edition 2 - February 2021
The information management function and resources Lead appointed Subcontractor appointed party Information management assignment matrix: Appointingparty Appointed party Building services sub-contractor example party Key: R Responsible for undertaking activity/task party task A Accountable for activity/task completion engineer controller engineer surveyor C Consulted during activity/task third manager manager chain I Informed following activity/task completion Contractor technician(s) specialist ID Activity/task Source Client Client's Main Design Project Mechanical Electrical Quantity Document CAD BIM Supplyteams Submit information model for appointing party ISO 19650- 7.3 acceptance 2; 5.7.3 Submit information for appointing party review ISO 19650- 7.3.1 and acceptance within the project's common data I R R C C I A/R C R 2; 5.7.3 environment ISO 19650- 7.4 Review and accept the information model 2; 5.7.4 Review the information model in accordance with ISO 19650- 7.4.1 the project's information production methods and A/R A/R 2; 5.7.4 procedures Produce report at each information exchange of 7.4.2 n/a A/R I I I I the information model review carried out Information management process - Project close- ISO 19650- 8 out 2; 5.8 ISO 19650- 8.1 Archive the project information model 2; 5.8.1 Archive the information containers within the project's common data environment in ISO 19650- 8.1.1 A/R accordance with the project's information 2; 5.8.1 production methods and procedures ISO 19650- 8.2 Capture lessons learned for future projects 2; 5.8.2 Arrange and chair a lessons learned workshop (or include lessons learned within other agreed 8.2.1 n/a A/R I I I workshops) in accordance with workshops identified on the project programme Capture lessons learned (using the lessons learned template) during the project. The lessons learned should be maintained throughout the ISO 19650- 8.2.2 A/R I I I project and uploaded to the project’s common 2; 5.8.2 data environment or other agreed central knowledge store
20 | Guidance Part A Edition 2 - February 2021
The information management function and resources Some tasks may be required that are not 1.5 What are the competencies explicitly covered by the clause activities within the ISO 19650-2 information that need considering? management process. For example, the review of tender responses is not specifically covered It is important to ensure that individuals have but this is a necessary activity to move from the necessary skills and behaviours to fulfil the the tender response stage to the appointment activities and tasks they have been allocated stage. as part of the information management function. Competencies of individuals across Key points to note a task team should be considered to ensure the most appropriate individual(s) is selected • Time and effort may be required to when allocating specific activities and tasks. schedule out tasks and agree responsibility and accountability. However, this should The following competencies may be required pay-off by helping individuals to clearly to support the activities and tasks as part of understand their required input into to their the information management function: organization’s information management function. Technical • Assigning activities and tasks across the • Project delivery experience of projects of delivery team should reduce dependence a similar scale and complexity including on the BIM/digital specialist and help understanding of typical roles and to embed and upskill information responsibilities and understanding of management capabilities to existing job contracts roles appropriately. • Understanding and application of appropriate national and international standards related to information management and BIM • Software skills (appropriate to the information management activities and tasks). Non-technical • Resilience (to engage with and encourage behavioural change) • Planning and organization • Research and investigating • Analysis and problem solving • Initiative/independence • Results driven/quality orientation. It is vital that individuals possess good communication skills and understand the importance of teamwork to improve collaborative working.
21 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.6 Delegating the information
management function
1.6.1 Delegation of authority in ISO 1.6.2 Probity arrangements
19650-2 clauses 5.1.1 and 5.3.1 Probity is “the quality of having strong moral Under clause 5.1.1 the appointing party can principles; honesty and decency”1. delegate the responsibility for all or part Probity arrangements are specifically of the information management function to noted under ISO 19650-2 clause 5.3.1 (lead the prospective lead appointed party or a appointed party information management third party. Similarly, clause 5.3.1 allows a function) but not under clause 5.1.1 (appointing prospective lead appointed party to delegate party). However, probity arrangements may their responsibility to a prospective appointed be applicable to either the appointing party party or third party. Responsibility can be or lead appointed party. delegated, but accountability remains with the party identified in each clause from In practical terms, probity arrangements mean ISO 19650-2 (refer to guidance Figure 2). ensuring that any potential conflicts of interest are identified and managed. An accountable organization is the organization who is ultimately answerable For example, on project X the review and for the activity. This includes “yes” or acceptance of the information model is carried “no” authority and veto power. Only one out on behalf of the appointing party by a accountable organization can be assigned to lead appointed party who is the architect on an activity. the project. This means that the architect is responsible for both producing information and for reporting to the appointing party on The responsible organization is the compliance with the prescribed information organization who completes the activity requirements. To avoid any potential conflict, or task. The responsible organization is it may be necessary to identify different responsible for action/implementation of individuals within the architect’s organization activities and tasks that have been delegated to carry out the required functions. to them. Individuals within the same organization would always therefore need to maintain The authority will typically be delegated honesty and decency to avoid any potential where the appointing party or lead appointed conflicts of interest. party do not have sufficient capability or capacity to carry out specific tasks. Where the appointing party or lead appointed party requires a third party to carry out all or part of the information management function on their behalf they might require the prospective third party to demonstrate how they will deal with any possible conflicts of interest as part of their tender response. This could be, for example, by confirming membership of a professional body that includes the need to maintain honesty and decency. Or the third party may be asked to provide a statement, organization structure or plan on how conflicts will be managed within their organization.
1 Oxford English Dictionary
22 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.7 Engaging a third party to undertake the information
management function
1.7.1 Principles 1.7.2 Information to be provided to the
third party Where an organization requires assistance with all or part of their information In order to appoint a third party, it is management function, they may choose important to provide sufficient information to engage a third party to assist. In this about the project at the invitation to tender situation, the third party will be responsible stage to enable a comprehensive proposal for completing agreed tasks on behalf of to be returned by the prospective third the appointing organization. However, as party. This should include general project noted earlier the organization appointing the information along with an anticipated project third party still retains the accountability to duration and the procurement methodology (if satisfy the information management functions known). identified by ISO 19650. In terms of delivery of the information Where a third party is engaged, they are management activities, it is also important to effectively a lead appointed party under the share details of any other parties involved in ISO 19650 series. However, they would not the project and their capabilities (if known), be expected to submit a tender response any existing processes and any specific containing the same information resources technology being used or intending to be that other lead appointed parties would used. This is so that the third party fulfilling provide (i.e. they would not need to provide the information management activities and the resources identified in Table 2). This is tasks can consider the delivery strategy as because they are carrying out activities on part of their own appointment. behalf of the appointing party and are not an information provider in the same context as a Where a third party is being appointed by delivery team lead appointed party. a lead appointed party, the lead appointed party will need to include all relevant information management resources including the appointing party’s exchange information requirements, the project’s information standard and so on. It is important to identify what activities and tasks will be performed by all parties across a project when establishing a proposed scope of services for a third party. This will help ensure that there are no gaps in the information management function across the project team (refer to examples of the detailed RACI matrices provided earlier).
23 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.7.3 A proposed structure for an
invitation to tender when appointing a third party Clause 5.1.1 of ISO 19650-2 requires the I. Tender response requirements appointing party to establish a scope of a. Fee proposal (against tasks) services where they wish to appoint a lead b. Fee drawdown (against programme) appointed party or third party to undertake all or part of the information management c. Charge out rates (i.e. day rate(s)) and function. Likewise, clause 5.3.1 requires a costs (including travel/expenses)) prospective lead appointed party to establish d. Capability and competency a scope of services where they wish to appoint i. Demonstration of capability a prospective appointed party or third party (i.e. case studies including to undertake all or part of the information references) management function. ii. Demonstration of competency (i.e. CVs) The following structure could be used to form the basis for an invitation to tender to e. Proposed delivery methodology appoint a third party to carry out all or part f. Assumptions the information management function for g. Exclusions either an appointing party or prospective lead h. Probity arrangements (if applicable) appointed party: i. Observations on supporting A. Record of issue / document control information provided (if applicable) j. Other supporting information relevant B. Introduction to the commission C. Project details (to communicate sufficient J. Tender return procedures (including understanding of the project for the return date, person(s) to return tender to) third party to be able to submit a tender K. Tender evaluation criteria response) L. Appointment (proposed date for a. Key project information (including confirmation of successful/unsuccessful project name, project description, tenderer and feedback to unsuccessful project value and procurement route tendering organizations). (if known)) b. Programme (if known) c. Team (if known) d. Relevant technology solutions (if known) D. Supporting information E. Tasks* F. Terms and conditions G. Authority H. Required competency I. Probity requirements (if applicable) * Including required tasks and allowing the third party to add any additional services or costs (such as technology costs) that may be required to manage the information activities and tasks effectively.
24 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.8 Information management assignment matrix
The UK BIM Framework has developed an The intention of providing this tool is to information management assignment matrix encourage a standardized starting point tool based on the RACI matrix in ISO 19650- for project specific and organizational
2 Annex A. It provides an expanded list of adaptation. Examples of how this might be
tasks against each clause activity that should adapted for a specific organization are shown be assigned across the project team to fulfil in Figures 4 and 5 in this guidance. the information management function. It also includes a task for producing the project’s Note: There should be consideration to how information protocol and the key tasks from any information management assignment ISO 19650-5 that need considering for the matrices could be joined up between parties, appointing party’s information management and how these are updated throughout the function. delivery phase of a project. In the first instance the tool should be used To be as useful as possible, the tool is by the appointing party to assign out the provided in multiple formats (Database information management function across the [Airtable available for viewing as well as CSV project team (columns have been provided download], Word and Excel). to allow for any third-party information management appointments if required). Accountability ‘A’ is fixed as per the ‘shall’ clauses in ISO 19650-2 and shouldn’t be changed, however responsibility ‘R’, consulted ‘C’ and informed ‘I’ can be adapted as required. In the second instance the tool could be useful for those applying ISO 19650-2 on projects to help assign their information management function to individuals specifically within their team. It is envisaged there will be a need to adapt it as required to include any subtasks specific to an organization (while removing other parties’ tasks), and a desire expand to capture individuals’ names or project roles.
25 | Guidance Part A Edition 2 - February 2021
The information management function and resources
1.9 Conclusion
Information management is a critical component of successful project delivery and asset operation. The information we produce during the lifecycle of an asset informs decision making throughout; we therefore need to treat information with the same importance as the physical asset(s) it represents. In terms of the ISO 19650 series, the information management function should be the very first consideration for ANY organization engaged in either project delivery or asset operation. Assigning responsibility and authority for the activities making up the information management process will help individuals to ensure the best possible information outcomes. Individuals fulfilling information management function activities should have the required competencies. Where there are identified shortfalls of competencies and experience, these should be addressed by upskilling individuals, or by appointing a third-party specialist. Discharging the responsibility for information management function activities to a prospective lead appointed/appointed party is permitted but probity arrangements should be carefully considered.
26 | Guidance Part A Edition 2 - February 2021
The information management function and resources
2.0 About ISO 19650 resources
Author: Sarah Davidson The University of Nottingham
2.1 ISO 19650 resources
The ISO 19650 series references resources and In terms of the resources referenced in ISO content that should be created for successful 19650- 2, it is possible for resource content information management (using building to be combined with other design and information modelling). construction project content. However, care should be taken to ensure that resources: This guidance refers to these as resources and not documents because: • Are not incorrectly promoted as appointment (and therefore contractual) • They do not need to exist as documents resources and equally are not demoted – their content could be referenced via a from being appointment resources system • Are authored at the right level (project • They do not need to stand alone – their or appointment). An appointment level content might be combined with other resource should not contain project content wide content that is not relevant to the appointment. • The emphasis is on the existence of content, not how the content is transported. Consideration should also be given to how The ISO 19650 series also refers to “shared resource content cascades through the resources”. Shared resources can take many delivery team. Combining content could forms, such as document templates, 3D potentially either aid or complicate this. object libraries or custom line styles and Note 1: Table 3 and Figure 6 list and ISO 19650-2 clause 5.1.6 provides examples. illustrate all the compulsory resources from Shared resources are one type of resource ISO 19650-2 and 3. There could also be that are produced during the information further resources depending on the approach management process taken to the information management function and provision of the common data environment, but these are not identified here. Note 2: Table 3 and Figure 6 will be updated as standards within the ISO 19650 series are released.
27 | Guidance Part A Edition 2 - February 2021
The information management function and resources Table 3: ISO 19650-2 resources Resource ISO Resource/content Created by 19650 Originating clause Level Status Part Organizational Appointing Organization For 3 5.1.2 Establish the information requirements party information organizational information requirements Asset information Appointing Asset For 3 5.1.4 Establish the asset requirements party information information requirements Project’s information Appointing Project For 2 5.1.2 Establish the project’s requirements party information information requirements Project’s information Appointing Project For 2 5.1.3 Establish the project’s delivery milestones party information information delivery milestones Project’s information Appointing Project Appointment 2 5.1.4 Establish the project’s standard party information standard Project’s information Appointing Project Appointment 2 5.1.5 Establish the project’s production methods and party information production procedures methods and procedures Reference information Appointing Project Appointment 2 5.1.6 Establish the project’s party reference information and shared resources Shared resources Appointing Project Appointment 2 5.1.6 party Project’s information Appointing Project Appointment 2 5.1.8 Establish the project’s protocol party information protocol Exchange information Appointing Appointment Appointment 2 5.2.1 Establish the appointing requirements party party’s exchange information requirements Tender response Appointing Appointment For 2 5.2.3 Establish tender response requirements party information requirements and evaluation criteria Tender evaluation criteria Appointing Appointment For 2 5.2.3 Establish tender response party information requirements and evaluation criteria (Pre-appointment) BIM Lead Appointment For 2 5.3.2 Establish the delivery execution plan appointed information team’s (pre-appointment) party BIM execution plan High level responsibility Lead Appointment For 2 5.3.2 Establish the delivery matrix appointed information team’s (pre-appointment) party BIM execution plan Proposed information Lead Appointment For 2 5.3.2 Establish the delivery delivery strategy appointed information team’s (pre-appointment) party BIM execution plan Proposed federation Lead Appointment For 2 5.3.2 Establish the delivery strategy appointed information team’s (pre-appointment) party BIM execution plan Proposed schedule of Lead Appointment For 2 5.3.2 Establish the delivery software, hardware and IT appointed information team’s (pre-appointment) infrastructure party BIM execution plan Assessment of task team Appointed Task team For 2 5.3.3 Assess task team capability and capacity party information capability and capacity
28 | Guidance Part A Edition 2 - February 2021
The information management function and resources Resource ISO Resource/content Created by 19650 Originating clause Level Status Part
Summary of the delivery Lead Appointment For 2 5.3.4 Establish the delivery
team’s capability and appointed information team’s capability and capacity party capacity Proposed mobilization plan Lead Appointment For 2 5.3.5 Establish the delivery appointed information team’s mobilization plan party Risk register Lead Appointment For 2 5.3.6 Establish the delivery appointed information team’s risk register party Delivery team’s BIM Lead Appointment Appointment 2 5.4.1 Confirm the delivery team’s execution plan appointed BIM execution plan party Detailed responsibility matrix Lead Appointment For 2 5.4.2 Establish the delivery team’s appointed information detailed responsibility party matrix Information delivery strategy Lead Appointment Appointment 2 5.4.1 Confirm the delivery team’s appointed BIM execution plan party Schedule of software, Lead Appointment Appointment 2 5.4.1 Confirm the delivery team’s hardware and IT appointed BIM execution plan infrastructure party Lead appointed party’s Lead Appointed Appointment 2 5.4.3 Establish the lead exchange information appointed party appointed party’s exchange requirements party appointment information requirements Task information delivery Appointed Task team Appointment 2 5.4.4 Establish the task plan party information delivery plan(s) Master information delivery Lead Appointment Appointment 2 5.4.5 Establish the master plan appointed information delivery plan party Lessons learned Appointing Appointment For 2 7.8.2 Capture lessons learned for party information future projects
29 | Guidance Part A Edition 2 - February 2021
The information management function and resources Figure 6: ISO 19650-2 resources map Asset Invitation to tender resources Organizational information information requirements* requirements Exchange information requirements Project’s Project's information standard information requirements Project’s information production methods and procedures Project’s information Project's reference information delivery milestones Project’s shared resources Project's information protocol Tender response requirements Tender evaluation criteria 1. The appointing party generates and issues the invitation to tender resources Prospective lead appointed party tender response 2. The prospective lead appointed party submits their Delivery team’s (pre-appointment) BEP considering: tender response Details of individuals Proposed information delivery undertaking the information strategy management function High level responsibility Proposed federation strategy matrix Proposed adds/amends to project’s information Proposed adds/amends to production methods and project’s information standard procedures Proposed schedule of software, hardware and IT infrastructure +
Summary of the prospective delivery team’s capability +
capacity + Proposed mobilization plan + Risk register Resource generated to support the tender response Assessment of task team capability and capacity Figure 6: ISO 19650-2 resources map
30 | Guidance Part A Edition 2 - February 2021
The information management function and resources 3. The appointment resources are completed for the lead appointed party. Appointment resources are then completed for each appointed party as they join the delivery team. Lead appointed party Appointed party appointment resources appointment resources Lead appointed party’s exchange Exchange information requirements information requirements Agreed project's information standard Agreed project’s information standard Agreed project’s information Agreed project’s information production methods and procedures production methods and procedures Project’s reference information Project’s reference information Project’s shared resources Project's shared resources Project’s information protocol Project's information protocol + Delivery team’s BEP including: Delivery team’s BEP Information Details of + delivery strategy individuals (updated as Task information delivery plan (TIDP) undertaking required) the information Federation management strategy (updated function as required) High level responsibility matrix (updated as required) Confirmed schedule of software, hardware and IT infrastructure + Master information delivery plan (MIDP) Resource generated to support appointment resources Detailed responsibility matrix Key: Created by the appointing party Created by the (prospective) lead appointed party. Resources do not progress to become appointment resources Created by the (prospective) lead appointed party. Resources progress to become appointment resources Created by the (prospective) appointed party Created by the lead appointed party and inform project level To indicate how one resource informs another resources To indicate static resources
31 | Guidance Part A Edition 2 - February 2021
The information management function and resources
3.0 Summary
ISO 19650 guidance A has provided further insight into the information management function and information management resources. It should be referred to by practitioners and those implementing the ISO 19650 series across a project, within an appointment or within an organization. Please note that the ISO 19650 series is still new, albeit based on former UK standards. As experience of implementing the ISO 19650 series is gained over the coming months and years, this guidance will be updated to reflect both this experience and any comments/ feedback received from users. Please do let us have your feedback by emailing us at guidancefeedback@ukbimframework.org. Please also remember that standards within the ISO 19650 series are available at www.bsigroup.com. Visit www.ukbimframework.org to see how the ISO 19650 standards plus other standards within the UK BIM Framework map to the design, build, operate and integrate process.